Power Transmission & Distribution
Apart from the generation of electricity, PPM was also involved in energy transmission and distribution projects under the Sarawak Corridor of Renewable Energy (SCORE), including the 500 kV Backbone Transmission Line Project and a number of substation projects.
500KV BACKBONE TRANSMISSION LINE PROJECT
Project Controls | Contract Management & Administration | Cost Management | Reporting | Claims Preparation | Claims Evaluation | Risk Management
Client: Sarawak Cable Berhad (holding company of Trenergy Infrastructure Sdn. Bhd.)
Project Timing: 2014-2017
Sinohydro (Corporation) M Sdn. Bhd. - Trenergy Infrastructure Sdn. Bhd. JV was appointed by Sarawak Energy as the contractor for Packages B & C of the 500 kV Transmission Backbone Project. This involved the construction of two sections of the 500kV backbone - Mapai to Lachau (Package B) and Lachau to Tondong (Package C).
PPM was appointed as the Project Controller by Sarawak Cable, and our roles included:
Project Controls | Contract Management & Administration | Cost Management | Reporting | Claims Preparation | Claims Evaluation | Risk Management
Client: Sarawak Cable Berhad (holding company of Trenergy Infrastructure Sdn. Bhd.)
Project Timing: 2014-2017
Sinohydro (Corporation) M Sdn. Bhd. - Trenergy Infrastructure Sdn. Bhd. JV was appointed by Sarawak Energy as the contractor for Packages B & C of the 500 kV Transmission Backbone Project. This involved the construction of two sections of the 500kV backbone - Mapai to Lachau (Package B) and Lachau to Tondong (Package C).
PPM was appointed as the Project Controller by Sarawak Cable, and our roles included:
- Setting up baseline with cost and resource loading and Earned Value Management Monitoring Regime, and updating programmes on a regular basis;
- Leading the compilation of internal and external reporting;
- Creating and maintaining internal budget which aligns with the requirements of the Headquarters, reviewing subcontract claims, submitting claims and variations to the Client, working with the project team on final accounts;
- Keeping track of all costs and maintaining cost-related documentation;
- Maintaining a risk register and obtaining updates from risk owners and conducting risk workshops;
- Supporting the Project Director by identifying the procedural parts of the main and sub-contracts and maintaining a register of all contract-related matters.
SARAWAK ENERGY BERHAD'S SUBSTATIONS
Design Management | Project Management | Contract Management & Administration | Project Controls | Stakeholder Management | Health & Safety Management
Client: Sarawak Energy Berhad (SEB)
Project Timing: 2018-2022
Sarawak Energy Berhad (SEB) engaged PPM to plan and manage the civil, mechanical and electrical engineering, as well as the contract administration and safety management aspects of some of their electrical substation projects. Essentially, the work scope involves the design and construction of electrical substations including contract administration and management. Some of the substation projects are designated as fast-track projects by SEB.
PPM provides management and technical support, which covers:
Design Management | Project Management | Contract Management & Administration | Project Controls | Stakeholder Management | Health & Safety Management
Client: Sarawak Energy Berhad (SEB)
Project Timing: 2018-2022
Sarawak Energy Berhad (SEB) engaged PPM to plan and manage the civil, mechanical and electrical engineering, as well as the contract administration and safety management aspects of some of their electrical substation projects. Essentially, the work scope involves the design and construction of electrical substations including contract administration and management. Some of the substation projects are designated as fast-track projects by SEB.
PPM provides management and technical support, which covers:
- Management of engineering design and construction;
- Contract administration and management;
- Liaison with local authorities;
- Review and monitoring of contractor’s design and construction works;
- Ensuring all necessary safety requirements are met; and
- Ensuring the final delivery of work within the scheduled timelines.
- Kanowit 132/33/11 kV Substation
- Tatau 275/(132)/33/11 kV Substation
- Sibiyu 132/33 kV Substation
- Bunut (500)/275/(132)/33 kV Substation
- Kemena 275 kV Substation Extension Project